Midway Road (County Road 712) Widening Projects

District Office
Steven C. Braun, P.E.
District Four Secretary

3400 W Commercial Blvd
Fort Lauderdale, FL 33309

Tel: 866-336-8435
Fax: 954-777-4528

Additional Contacts
Staff Directory

Welcome

The Florida Department of Transportation (FDOT) District Four is designing a 1.6 mile segment of Midway Road (CR 712) in St. Lucie County. The project will be completed in two segments:

1.) Glades Cut-Off Road to Jenkins Road (231440-4)
2.) Jenkins Road to Selvitz Road (231440-5)

The project limits are shown on the location map below. The proposed projects widen the existing two-lane roadway to a four-lane divided road, inclusive of 7-foot buffered bike lanes in both directions. In addition, the project will include a 12-foot bicycle / pedestrian path on the south side of the road, and a 6-foot sidewalk along the north. The design project improves safety and allows opportunities for pedestrian, bicycle, and transit facilities. The project includes the replacement of the existing bridge over Florida's Turnpike.

Working with the key stakeholders: St. Lucie County, St. Lucie Transportation Planning Organization (TPO), Florida's Turnpike Enterprise (FTE), the scope of the project has expanded to include a new partial interchange with Florida's Turnpike. The design of the new partial interchange (FPID: 451858-1) will be led by Florida's Turnpike Enterprise and includes a northbound off-ramp, and southbound on-ramp. The partial interchange will be constructed in conjunction with the Midway Road segment from Glades Cut-Off Road to Jenkins Road (231440-4). For more information please visit www.midwayramps.com (coming soon).

We are pleased to announce that the Midway Road projects have been identified as a congestion relief project (number 18) under Governor DeSantis's Moving Florida Forward Infrastructure Initiative helping to secure and advance construction funding. Please visit www.FDOT.gov/movingfloridaforward for more information.

Click on the various project resources for information about the design process, future public meetings, the project schedule, and information on how to contact FDOT's project manager.

Project At-A-Glance

District
Four

Design Start Date
Design started in February 2017.

Jenkins Road to Selvitz Road
FIN: 231440-5-52-01

Design
Complete

Construction Start Date
Fall 2023

Anticipated Completion Date
Summer 2025

Construction Cost Estimate
$24 million


Glades Cut-Off Road to Jenkins Road
FIN: 231440-4-52-01

Design Completion
Design is anticipated to begin Winter 2023 and be complete in Summer 2026

Construction Start Date
Summer 2027

Anticipated Completion Date
Winter 2029/30

Construction Cost Estimate
$50.4 Million

Consultant
Inwood Consulting Engineers, Inc.

Project Manager
Haiyan Ou, P.E.

Midway Road Project Location Map
Click here to view the project location in a larger map

Midway Road/County Road (CR) 712 Project
Financial Project IDS: 231440-4-52-01; 231440-5-52-01
ETDM No.: 14177

FIN: 231440-4-52-01 
Glades Cutoff Road to Jenkins Road

FIN: 231440-5-52-01
Jenkins Road to Selvitz Road

FIN: 451858-1-52-01
Midway Road at Florida's Turnpike Partial Interchange
www.midwayramps.com (coming soon)